Answer

How long does commercial solar installation take?

A UK commercial solar installation takes 2–12 weeks on-site depending on system size. Including DNO G99 approval, structural survey and commissioning, the full project timeline from signed order to first generation is typically 3–6 months. A 100 kWp rooftop system takes about 3–4 weeks on-site; a 1 MWp system takes 8–12 weeks.

Last updated 26 July 2026.

Key facts at a glance

50 kWp system1–2 weeks on-site
100 kWp system3–4 weeks on-site
250 kWp system4–6 weeks on-site
500 kWp system6–8 weeks on-site
1 MWp+ system8–12 weeks on-site
DNO G99 approval45 working days statutory
Signed order → energisation3–6 months typical

The commercial solar project timeline

The gating item is usually DNO G99 approval, not the physical install. Structural survey (2–3 weeks), design and DNO application (2 weeks), DNO response (up to 45 working days), materials lead time (2–6 weeks) and install run in parallel where possible.

What extends the timeline

Anything requiring a new HV connection or substation upgrade adds 3–9 months. Listed buildings, conservation-area planning applications, or asbestos re-roofs each add 6–12 weeks. Requesting DNO early — during feasibility, not after design — usually eliminates the biggest risk.

Related reading

FAQ

Can commercial solar be installed while the business is operating?

Almost always yes. Most warehouse, factory and office solar installs happen with zero downtime — scaffolding and roof work run outside operational hours where needed. Final grid tie-in requires a short (typically 2–4 hour) power-down.

How long until the system generates electricity?

From physical completion, energisation is typically 1–2 weeks — the time to complete DNO commissioning tests and switch on export.

Free feasibility review

Request your free feasibility review

Share a few details and our team will send a no-obligation review of your site — indicative system size, annual generation, savings and payback. Prefer to explore numbers yourself first? Run the calculator or contact us directly.

  • MCS & RECC accredited installer
  • Response within one working day
  • No cost, no obligation
Try the calculator

By submitting you agree to be contacted about your enquiry. We don't share your details.