Guide · Grid connection

DNO G99 connection for commercial solar in the UK

Grid connection is one of the barriers to UK commercial solar deployment, alongside planning and finance. Here's how G99, G100 and ANM shape connection timelines and how to sequence your application.

Key takeaways

  • Commercial solar systems over 11.04kW three-phase require prior DNO approval via a G99 application before installation can begin.
  • For homes and small businesses, GOV.UK guidance states that the DNO will respond within 45 days for low-voltage devices and 65 days for high-voltage devices, either to approve installation or discuss amendments.
  • Submit your G99 application early in project planning to avoid installation delays, unexpected network upgrade costs, or export restrictions.

The G99 application process

1. Fast Track vs Full Study

GOV.UK guidance identifies a fast-track route using G99 Form A1-2 for Fully Type Tested Integrated Microgeneration and Storage installations. The installer must assess the proposed device and connection to determine the appropriate application route before installation.

2. Connection offer

Timelines vary massively by DNO and region. Straightforward offers land in 65 working days; constrained networks may take 6–12 months and include reinforcement cost estimates from £10k to £2M+.

3. Accept and pay

Offers are typically valid for 3 months. Reinforcement costs and pre-construction milestones lock in when you accept - think carefully before signing.

4. Commissioning & G99 witness test

Confirm the commissioning and witness-testing requirements with your DNO. The Solar Roadmap calls for DNOs, supported by the ENA and industry, to consider developing a common approach to witness testing.

How to avoid reinforcement

Options in order of impact: G100 zero export, ANM curtailment, oversizing DC vs AC (clipping), pairing solar with battery, and load-shift agreements. Together these can unlock connection in months rather than years.

Related reading

FAQ

What's the difference between G98 and G99?

G98 covers small-scale (≤16 A/phase, so ~3.68 kW single-phase or ~11 kW three-phase) - notification only. G99 covers everything above that, including all commercial solar.

How long is the DNO queue in 2026?

For projects up to 500 kW export: usually 3–12 months from application to energisation. Above 1 MW export in constrained regions (East England, parts of Scotland): 18–36 months and reinforcement costs are common.

What is G100 zero-export and when should I use it?

G100 concerns export limitation. For an installation classified as ‘apply to connect’, GOV.UK guidance requires an application before installation even where export is limited. Export limitation should not be treated as automatic permission to install.

What's an ANM zone?

Active Network Management zones let more generation connect to a constrained network by curtailing output when the network is congested. You'll get faster connection and lower cost, but expect 3–10% of forecast output lost to curtailment annually.

Can I add battery storage under the same G99 application?

Solar and battery storage can be considered together: GOV.UK guidance describes a G99 Form A1-2 route for Fully Type Tested Integrated Microgeneration and Storage installations. For non-firm battery connections, the Solar Roadmap recommends providing battery operating profiles to assist the network company's assessment.

Get help with a G99 or G100 application

Free feasibility review

Request your free feasibility review

Share a few details and our team will send a no-obligation review of your site - indicative system size, annual generation, savings and payback. Prefer to explore numbers yourself first? Run the calculator or contact us directly.

  • MCS & RECC accredited installer
  • Response within one working day
  • No cost, no obligation
Try the calculator

By submitting you agree to be contacted about your enquiry. We don't share your details.

Ready to see whether your roof could reduce your energy bills?